Project 2013 Introduction
Project 2013
Lesson 5 – Tracking Your Progress
The Task Usage view with the Work table applied allows you to enter actual and remaining work values for tasks and individual resources. While you can also use the Project Guide to track the amount of work completed on a task, you must split the view to enter work amounts for individual resources.
Entering actual work values
Procedures
1. Switch to the Task Usage view. 2. Apply the Work table. 3. To enter actual work completed, select the Actual field for the task or for the individual resource assigned to the task you want to update. 4. Enter the total number of hours of work completed on the task or the hours of work completed by the individual resource. 5. Press [Enter] . 6. To enter the remaining work, select the Remaining field for the task or for the individual resource assigned to the task you want to update. 7. Enter the total number of hours of work completed on the task or the hours of work completed by the individual resource. 8. Press [Enter] .
OFFICEPRO, Inc.
Page 131
Made with FlippingBook HTML5