Project 2013 Introduction
Project 2013
Lesson 3 – Working with Tasks
6. Press [Enter] .
Step-by-Step
From the Student Data directory, open HOUSE2.MPP .
Enter tasks.
If necessary, scroll the right pane of the Gantt Chart view until Jun 5, ‘16 appears.
Steps
Practice Data
1. Select the first empty field in the Task Name column.
Click in the first empty field in the Task Name column.
A border appears around the Task Name field and the mouse pointer changes into a cross.
2. Enter a task name.
Type Planning Phase.
The desired task name appears in the field.
3. Press [ Tab ] to get to the Task duration.
Press [Tab].
The task is entered; a bar appears on the Gantt chart for the task.
4. Enter the Task duration.
Type 1 and press [Enter].
The desired duration appears in the Duration field.
5. Select the next empty field in the Task Name column and enter a task name. The desired task name appears in the field.
Type Conduct Site Survey.
6. Press [ Tab ] to get to the Task duration.
Press [Tab].
The task is entered; a bar appears on the Gantt chart for the task.