Project 2013 Intermediate
Project 2013
Lesson 4 – Working with the Critical Path
E XERCISE
W ORKING WITH THE C RITICAL P ATH
Task
View the critical path and slack time, and assign overtime.
1. Open Rooms10 . 2. View the critical path. 3. Display all tasks.
4. Switch to the Detail Gantt view and view the slack bars. Scroll to view the slack bars for the 5 Renovate Board Room and 9 Paint Doors tasks. Notice the 2 days of free slack. 5. View the slack values for all tasks. ( Hint: Apply the Schedule table and drag the split bar.) 6. Add a Start No Earlier Than constraint to task 22 Install Computers. Set the date to 7/25/16 . Notice task 21 Install Computer Room Furniture now has a 14.5 days Total Slack.
7. Close the file without saving the changes.
OFFICEPRO, Inc.
Page 91
Made with FlippingBook - Online magazine maker