Project 2013 Intermediate
Lesson 5 – Working with Baselines
Project 2013
Steps
Practice Data
1. Select the Task tab.
Click
.
The Task ribbon is visible.
2. Select the Gantt Chart dropdown button. The Task View submenu appears.
Click
.
3. Select the Tracking Gantt.
Select
.
The Tracking Gantt view is displayed.
Select the first task and scroll to view the Gantt bars for the task. Scroll through the Gantt chart and notice that all the blue and red bars lay within the gray bars underneath.
U PDATING A P ROJECT B ASELINE
Discussion
Generally you should never update the baseline unless authorized in writing. If it becomes necessary to update the baseline, you can update the project’s baseline. Updating the baseline for the entire project overwrites all the data in the current baseline with the new information.
Updating a project baseline
Page 98