Lesson 5 – Working with Baselines
baseline saves the task, resource and assignment information for the project. Baseline is the baseline that is displayed on the Gantt Chart .
In addition to saving the duration of each task, baselines also save the start date, finish date, and all work and cost information for all tasks and assignments. Baselines also save resource information, which includes all work and cost data.
You can update additional baselines the same way you update the main baseline. You can save the entire project to an additional baseline or just selected tasks.
Procedures
1. Click
on the Project tab.
2. Select
in the Set Baseline submenu.
3. Click the drop-down arrow for the Set Baseline list and choose a Baseline.
4. Choose if this is for the entire project or selected tasks.
5. Click
.
Step-by-Step
Save an additional baseline.
Steps
Practice Data
1. Click the Set Baseline button on the Project tab. The Set Baseline submenu appears.
Click
.
2. Choose the Set Baseline... from the submenu. The Set Baseline dialog box opens.
Click
.