Lesson 5 – Working with Baselines
Steps
Practice Data
6. Select the list for the selected plan. A list of plans appears.
Click Clear interim plan .
7. Select the plan you want to clear. The plan is selected. 8. Select the Entire project or Selected tasks option. The desired option is selected.
Click Start1/Finish1.
Click
.
9. Select OK .
Click
.
The Clear Baseline dialog box closes and the baseline information is cleared.
Notice that NA now appears in the Start1 and Finish1 fields for the 3 Develop Blueprints task. Select the 3 Develop Blueprints task, if necessary, and open the Set Baseline dialog box. Restore the date information by saving the Start1/Finish1 interim plan for the selected task. Then, hide the Start1 and Finish1 columns.
Close HOUSE14.MPP .