Project 2013 Intermediate
Lesson 6 – Tracking Your Progress
Project 2013
be copied into the actual value fields. Values for incomplete tasks will be recorded according to the percentage of work assumed to have been completed. However, if you do not want to record information for incomplete tasks, you can choose to update tasks that have not yet started (0%) and those that are 100% complete only.
You can choose to update the work for an entire project or just for selected tasks. In addition, you can reschedule uncompleted work to start after a date that you specify.
The Update Project dialog box
NOTE
A Planning Wizard dialog box opens if the time span includes a task with a constraint or deadline date. To update selected tasks only, select them before opening the Update Project dialog box and then select the Selected tasks option.
Procedures
1. Select the Project ribbon. 2. Point to the Status group command. 3. Select the Update Project command. 4. Enter the desired date in the Update work as complete through box. 5. Select additional options as desired.
6. Select
.
7. If a Planning Wizard dialog box opens, select
.