Lesson 6 – Tracking Your Progress

4. Press [Enter] . 5. To enter a percentage using the Update Tasks dialog box, select the task you want to update. 6. Click the Update Tasks button on the Task ribbon, Schedule group. 7. Enter the actual percentage of work completed in the % Complete field.

8. Select

.

Step-by-Step

Enter the percent complete.

Display the Tracking table fields. Drag the split bar all the way to the right to display the % Complete field.

Enter a status date for the project of 7/25/16 in Project Information.

Steps

Practice Data

1. To use the table to enter the

Click in the % Complete field for the 10 Select Subcontractors task.

percentage of work complete, select the % Complete field for the desired task. The field is selected and the spin box appears.

Type 65.

2. Type the desired value.

The value appears in the % Complete field.

3. Press [Enter] .

Press [Enter].

The progress information is updated.

4. To enter a percentage using the Update Tasks dialog box, select the task you want to update. The desired task is selected. 5. Click the Mark on Track dropdown menu in the Schedule group on the Task ribbon. The dropdown menu appears.

Click the 10 Select Subcontractors task.

Click .