Project 2013 Intermediate
Lesson 7 - Customizing Project Information
Project 2013
Step-by-Step
Set scheduling options.
Switch to the Resource Sheet view and notice that the Max. Units field displays percentages.
Steps
Practice Data
1. Select the File tab.
Click
The File Backstage appears.
2. Select the Options command. The Options dialog box opens.
Click
.
Click
3. Select Schedule .
The Schedule page appears.
.
Click Show assignment units as a: .
4. Select the Show assignment units as a: list. A list of options appears.
5. Select the desired option. The option is selected.
Click
.
Select the Duration is entered in: list and select .
6. Continue to change the scheduling options as desired. The desired options are changed.
7. Select OK .
Click
The Options dialog box closes and the scheduling settings are saved.
Notice that the Max. Units column now displays decimals.
Switch to the Gantt Chart view and create a new task in the first blank Task Name field with the name Final Report . Type 2 in the Duration field and press [Enter] . Notice that the duration is 2 hrs instead of 2 days . Create another task in the next empty field by typing Review Report in the Task Name field and pressing [Enter] . Notice that the default duration is an estimated 8 hrs .