14. Assign the Cable Installation calendar to the 17 Install Network Cable task. Point
to the task bar to see that the duration of the task is 1 day but the task bar spans
3 days since the task can only be worked on for four hours each day.
15. Switch to the Resource Sheet view. Change the availability of the 3 Painter
resource to show that three painters (300%) are available full-time during till
7/31/16 but only two painters (200%) are available after 8/1/16
16. Close the file without saving the changes.