Project 2013 Intermediate

Lesson 2 – Adjusting Resources

Project 2013

that the Electrician resource is overallocated during the seventh month of the project, additional electricians could be hired for that one month period.

Procedures

1. Switch to the Resource Usage view.

2. Double-click the overallocated resource to which you want to add units.

3. Select the General tab.

4. Select the Units field in the Resource Availability table.

5. Enter the new unit value in the Units field in the Resource Availability table.

6. Select

.

Step-by-Step

Resolve resource conflicts by increasing units.

If necessary, switch to the Resource Usage view.

Scroll as necessary to view the 2 Painter resource during the week of Oct 23,  16 . Notice that the resource name and work values are in red, indicating that the resource is overallocated.

Steps

Practice Data

1. Double-click the overallocated

Double-click the 2 Painter resource in the Resource Name column.

resource to which you want to add units. The Resource Information dialog box opens.

2. Select the General tab.

Click

, if

The General page appears.

necessary.

3. Select the Units field in the Resource Availability table. The Units field is selected and a spin box appears in the field.

Click in the Units field.