Project 2013 Intermediate

Lesson 2 – Adjusting Resources

Project 2013

finish date is affected by leveling. You can also set options to control the leveling of multiple resources assigned to the same task and to allow tasks to be split.

The Resource Leveling dialog box

NOTE If you try to level a resource and leveling is not an option, a Microsoft Project dialog box will open, informing you of any problems and providing alternatives to leveling.

Procedures

1. Switch to the Resource Usage view.

2. Select the resource(s) you want to level if you are only leveling selected

resources.

3. Click the Resource tab.

4. Click

in the Level group.

5. Select

.

6. Select the Entire pool option to level all resources or the Selected resources

option to level only the resources that are currently selected.