Lesson 2 – Adjusting Resources
The Resource Allocation view
Procedures
1. Switch to the Resource Allocation view.
2. Select the resource name in the top pane associated with the task you want to
delay.
3. Select the Leveling Delay field in the bottom pane for the task you want to delay.
4. Enter the desired delay amount.
5. Press [Enter] .
Step-by-Step
Level a resource by entering a delay amount.
If necessary, switch to the Resource Sheet view and notice that the 1 Laborer resource appears in red, indicating that it is overallocated.
Click the down arrow on the right side of the Resource Sheet button and select More Views. Switch to the Resource Allocation view. Drag the vertical split bar to the right until the Leveling Delay field appears in the bottom pane. Scroll the top pane as necessary to view the 1 Laborer resource that appears in red. Select the Laborer