Project 2013 Intermediate
Project 2013
Lesson 2 – Adjusting Resources
3. Select the Resource ribbon.
4. Select the Clear Leveling button.
Step-by-Step
Clear leveling.
If necessary, switch to the Resource Allocation view and view the tasks for the 1 Laborer resources.
Steps
Practice Data
1. Select the task associated with the leveling action you want to remove. The desired task is selected.
Click the 21 Install Windows task in the bottom pane.
2. Select the Resource tab.
Click
.
The resource ribbon is visible.
3. Select the Clear Leveling button. The Resource Leveling dialog box opens. 4. Choose Selected Tasks from the Clear Leveling dialog box. Selected Tasks is selected in the Clear Leveling dialog box.
Click
.
Choose
Selected Tasks.
5. Confirm the change. The dialog box closes.
Click
.
Notice that the 1 Laborer resource appears in red again, indicating that it is overallocated, and the leveling delay amount for the 21 Install Windows task changed back to 0 .
Use the View tab to remove the split pane and switch to the Resource Sheet view.