Project 2013 Intermediate

Project 2013

Lesson 2 – Adjusting Resources

Procedures

1. Select the Resource tab.

2. Select the

button in the Level group.

3. Select the Automatic option under Leveling Calculations .

4. Change any other leveling options as desired.

5. Click

.

6. Select the Entire pool or Selected resources option, if applicable.

7. Click

, if applicable.

Step-by-Step

Change leveling to automatic.

Switch to the Resource Sheet view. Select the 1 Laborer resource, which appears in red, indicating that it is overallocated.

Steps

Practice Data

1. Select the Resource tab.

Click

.

The Resource ribbon appears.

2. Select the Leveling Options button. The Leveling Options dialog box opens. Click

3. Select the desired option under Leveling Calculations . The desired option is selected. 4. Change any other leveling options as desired. The desired leveling options are changed.

Click

Automatic.

Click Level entire project under Leveling range for ‘ file name’.

5. Select OK .

Click

The Resource Leveling dialog box closes, the automatic leveling feature is enabled, and the Level Now dialog box opens.