Viewing resource costs
NOTE You can access the Page Setup dialog box by selecting the File menu and the Page Setup command or by selecting the Page Setup button in the Print Preview window. Microsoft Project also contains reporting features that print a variety of reports.
Procedures
1. Switch to the Resource Usage view.
2. Select the View ribbon.
3. Select Tables in the Data group.
4. Select the Cost table.