Project 2013 Intermediate
Lesson 3 – Assigning Costs
Project 2013
Procedures
1. Switch to the Gantt Chart view.
2. Select the View ribbon.
3. Click
button.
4. Select the Cost table.
Step-by-Step
View task costs.
Switch to the Gantt Chart view.
Steps
Practice Data
1. Select the View tab.
Click
.
The View ribbon appears.
2. Click the Tables button
The Table ribbon appears.
Click
.
3. Select the Cost table.
Click Cost table.
The Cost table is applied to the view and cost information appears.
Drag the vertical split bar as far to the right as possible and then scroll to view the cost information.
A SSIGNING A F IXED C OST TO A T ASK
Discussion
When you assign a fixed cost to a task, it means that you know the total cost of the task and resource costs do not affect the task. The task does not need a resource