Project 2013 Intermediate
Lesson 4 – Working with the Critical Path
Project 2013
You can assign overtime work in the Task Form view with the Resource Work format applied. When you assign overtime, you enter the overtime hours in the Ovt. Work field. You do not change the value in the Work column since the total amount of work for the task is the same. By adding overtime, you are telling Microsoft Project that some of the work will be performed outside of the normal working hours on the calendar. Microsoft Project subtracts the overtime work from the total work and shortens the duration of the task to reflect the amount of work to be completed during regular working hours.
Assigning overtime
Procedures
1. Switch to the Gantt Chart view.
2. Select the View ribbon.
3. Select the Detail s check box in the Split View group.
4. Select Task Form in the dropdown.
5. Select the task in the top pane associated with the resource to which you want
to assign overtime.
6. Select the bottom pane.
7. Select the Task Form Tools tab/ Format ribbon.
8. Select the Work command in the Details group.
9. Select the Ovt. Work field in the bottom pane for the desired resource.