Lesson 5 - Working With Multiple Projects
Project 2013
Steps
Practice Data
4. Select the Subproject command. The Insert Project dialog box opens.
Click
.
Click the student data drive.
5. Select the drive containing the project you want to insert into the open file. A list of available folders appears. 6. Select the folder containing the project you want to insert into the open file. A list of available files appears. 7. Select the project you want to insert into the open project. The project is selected.
Double-click to select the student data folder.
Click Planning.mpp .
8. Select Insert .
Click
.
The Insert Project dialog box closes and the selected project is inserted into the open file as a summary task.
Repeat steps 3-8 for Structure and Infrastructure . Save the file as Dwell 18 . Click Yes to save all projects.
U NLINKING S UBPROJECTS
Discussion
When a subproject and master project are linked, changes made to either file affect the other. In addition, if the same subproject is inserted into several master projects, changes to any linked file automatically changes the other files. Although this may be desirable in some situations, you may want to change task information in a master project without affecting the original source file or other master projects. By unlinking the master and subproject files, you can save changes that are independent of the other file.