The Calculation section of the Advanced tab in the Options dialog box
Procedures
1. Switch to the Tracking Gantt view. 2. Select the File tab. 3. Select the Options command. 4. Select the Advanced tab. 5. Scroll to the Calculation Options for this project: section 6. Select the Calculate multiple critical paths option.
7. Select
.
S AVING A W ORKSPACE F ILE
Discussion
You may need to work in more than one file, but do not want to consolidate the files because they are unrelated or you prefer to keep them as separate files. Instead of opening each file individually, which can be time-consuming, you can create a