10. Display the Entry table in Resource Sheet view and change the standard rate of the carpet layer to $25/hr . Add two more Computer Technicians to a maximum of 4 units. 11. Close Company Pool and save the changes. 12. Open the Options dialog box and return the Show assignment units as an option to Percentage .