Using graphical indicators
NOTE You can also select a field from the Value(s) list to use as a value for comparison. You can enter a range of values in the Value(s) field for the test condition, is within . A range is entered by separating the values with a list separator character such as a comma ( , ). To specify a range between 25 and 50, you would type 25,50 . You can import existing indicator criteria from another project using the Import Indicator Criteria button in the Graphical Indicators dialog box.
Procedures
1. Select the Project tab
.
2. Point to Custom Fields . 3. Select the Task or Resource option, as desired. 4. Select the Type list.