Lesson 2 – Using More Customization Features
Project 2013
The Organizer dialog box
NOTE Microsoft Project does not allow you to restore the settings of the current view. In order to restore those settings, you must first switch views before you open the Organizer. You can reset any view, table, filter or group by using the dropdown and selecting the reset command
Procedures
1. Click the File tab and go to Info .
2. Click 3. Select the desired tab.
4. Select the Task or Resource option at the top of the page, if applicable. 5. Select the element in the ‘Global.MPT’ list box that you want to reset. 6. Select Copy to replace the element in the current project with the same element in the global template. 7. Select Yes . 8. Select Close .
Step-by-Step
Use the Organizer to reset defaults.