Lesson 2 – Using More Customization Features
apply to tasks. In addition, you can create up to 10 sets of custom outline codes, where you can only create one set of custom WBS codes for tasks
In order to enter the custom outline codes, you need to add the Outline Code (< custom code name> ) field to the view. Then, you can enter the appropriate code for each task or resource. If you do not enter the code in the proper format, a Microsoft Project warning box will advise you of this and indicate the correct format.
After creating a custom outline code, you can enter field data by inserting the custom field into a table. You can also add custom field values on the Custom Fields page in the Task Information or Resource Information dialog box.
Creating a custom outline code