Lesson 3 - Evaluating and Distributing Data
Field
Description
This field displays the earned value cost variance through the status date [CV = BCWP - ACWP]. A positive value indicates that costs are under budget and a negative value indicates tasks are over budget. This field displays the estimated cost at completion. It also reflects the expected cost of the task based on costs already incurred and costs planned for the remainder of the task. This field displays the budgeted cost at completion. It also reflects the baseline cost for a task. This field displays the variance at completion. It also reflects the difference between the baseline cost and the expected cost for a task [VAC = EAC - BAC].
CV
EAC
BAC
VAC
Viewing earned value data
NOTE
You can get help on an earned value field by pointing to a field name in the table and clicking the Help on link in the ScreenTip.