Lesson 3 - Evaluating and Distributing Data
Steps
Practice Data
1. Click the View tab.
Click
.
The View ribbon appears.
2. Click the Tables command. The Tables submenu appears.
Click
.
Click
3. Click the More Tables command. The More Tables dialog box opens.
.
Click Earned Value.
4. Select Earned Value in the Tables list box. Earned Value is selected.
5. Click Apply .
Click
.
The table is applied to the view and the earned value data appears.
Note : SV, CV and VAC values in parentheses means the tasks cost more or were behind schedule.
Drag the split bar as far right as possible to view the earned value data.
V IEWING E ARNED V ALUE I NDICATORS
Discussion
The earned value tables of schedule and cost indicators allow you to analyze the progress and trend of your project. With this information you can judge if you are running ahead of schedule, on schedule, or behind schedule, and if you have enough money to complete the project. You can then make adjustments and prepare for future needs. These tables are available for task views only.
The Earned Value Cost Indicators table includes the BCWS, BCWP, CV, BAC, EAC, VAC fields and the additional fields below: