Project 2013 Advanced
Lesson 3 - Evaluating and Distributing Data
Project 2013
If necessary, drag the split bar to the right to view the SV% and SPI fields. Change the project status date by two week intervals and note the changes in earned values. Tasks with a negative SV% value and a SPI value less than 1 are behind schedule.
Practice the Concept: Apply the Earned Value Cost Indicators table.
V IEWING R EPORTS
Discussion
One of the newest features in Project 2013in the Reports section. It lets you show off project data with a whole new set of reports. The raw data presented in Project 2010 and in previous versions are now presented using more user-friendly and more professionally-formatted reports.
The Project tab is available for the user to create different reports. You can choose reports from the following categories: New Report , Dashboard, Resources, Cost, In Progress, Getting Started, Custom, and Recent.
Procedures
1. Select the Report tab. 2. Click the desired report category. 3. Select the desired report.
Step-by-Step
Create a resource report. Open HOUSE16.MPP , if necessary.
Steps
Practice Data
1. Select the Report tab.
Click
.
The Report ribbon appears.
Page 62