Project 2013 Advanced
Lesson 4 - Finalizing a Project
Project 2013
M ARKING T ASKS C OMPLETE
Discussion
When your project is finished, all tasks should be marked as 100% complete. Often, some tasks may be overlooked and not marked complete, even though the project has ended. You should mark all tasks as 100% complete before beginning your analysis of the actual information versus baseline information.
Procedures
1. Switch to the Gantt Chart view. 2. Filter for Incomplete Tasks . 3. Select the Task ribbon. 4. Select all the incomplete tasks.
5. Click the 100% Complete button
.
Step-by-Step
From the Student Data directory, open HOUSPRJ1.MPP . Mark tasks complete.
If necessary, switch to the Gantt Chart view.
Filter for Incomplete Tasks and then select the Task ribbon.
Steps
Practice Data
1. Select all the incomplete tasks.
Click the gray button at the intersection of the ID column and field name row.
All the incomplete tasks are selected.
2. Click the 100% Complete button. The selected tasks are marked complete.
Click
.