5. Select the Rollup option.

6. Select

.

Step-by-Step

Roll up Gantt bars to a summary task bar.

Scroll as necessary to view the Gantt bar for the 10 Build Foundation summary task.

Steps

Practice Data

1. Select the subtask you want to roll up. The desired subtask is selected.

Click the 11 Dig Foundation task

2. On Tasks tab, click the Task Information button.

Click

.

The Task Information dialog box opens.

3. Select the General tab.

Click the

tab, if

The General page appears.

necessary.

4. Select the Rollup option.

Click

.

The Rollup option is selected.

5. Select OK .

Click

.

The Task Information dialog box closes and the Gantt bar for the selected subtask is rolled up to the summary task bar.

Practice the Concept: Roll up the Gantt bar for the 12 Pour Foundation task.

View the rolled up Gantt bars. Notice that the Gantt bars were also rolled up to the Build Structure summary task bar since the Build Foundation summary task is a subtask of the Build Structure summary task.

Select both the 11 Dig Foundation and 12 Pour Foundation tasks. Use the Task Information button to open the Multiple Task Information dialog box. On the General page deselect the Rollup option and select OK . Notice that both rolled up bars no longer appear in the Gantt bar view.