Project 2016 - Introduction
Lesson – Scheduling Tasks
Project 2016
6. To move a linked task, select the ID number for the row containing the task you want to move. 7. Move the task to the new position.
Step-by-Step
Modify linked tasks.
Steps
Practice Data
1. To insert a new task between linked tasks, select the task above where you
Click the 4 Draft Proposal task
want to insert the new task. The linked task is selected.
2. Insert the new task.
On the Task ribbon Insert group Task drop-down menu, select Insert Task . Type the task name Review Blueprints . Accept the default duration of 1 day? Notice that the new task is linked by a Finish- to-Start relationship. Click 4 Review Blueprints task. Press the [Delete] key to delete the task. Notice that the Develop Blueprints and Draft Proposal tasks are now linked by a Finish-to-Start relationship. Use the Undo button to reverse the action.
The new task is inserted, with the links maintained, if appropriate.
3. To delete a linked task, select the task you want to delete. The task is selected.
4. Delete the new task.
The task is deleted with the links maintained, if appropriate.
Close HOUSE4.MPP .