Project 2016 - Introduction

Project 2016

Lesson – Working with Views

Step-by-Step

Use a combination view.

If necessary, switch to the Gantt Chart view.

Steps

Practice Data

1. Select the View ribbon. The View ribbon appears.

Click

.

2. Select the Details checkbox.

Click

The window splits horizontally into two panes to display a combination view and the default view, Task Form, appears in the View ribbon.

.

3. Select task 4 Draft Proposal

Accept the Task Form View.

The information in the bottom pane changes to display details for the task.

4. Deselect the detail checkbox.

Click

.

The view displayed in the upper pane of the combination window expands to occupy the entire window.

C HANGING THE V IEW IN A P ANE

Discussion

When you split a window, Microsoft Project provides default views in both panes. Change the view in either pane without affecting the other. This option allows you to adjust the views to display only the information you need. An active pane indicator on the left border of each pane identifies the view in that pane. The pane in which you are currently working displays a highlighted active pane indicator. The indicator is dimmed for the inactive pane.

The Calendar view and the Network Diagram view are the only views that cannot appear in the bottom pane. If you select the bottom pane and try to change it to this view, a message box appears stating that you cannot perform this action.