Project 2016 - Introduction
Project 2016
Lesson – Working with Calendars
Steps
Practice Data
3. Select Create New Calendar…
Click
The Create New Base Calendar dialog box appears.
.
4. Select the Create new base calendar or Make a copy of < calendar name > calendar option. The option is selected. 5. Select the Make a copy of
Click
Make a copy of
< calendar name > calendar , if necessary.
Click the Make a copy of .
Click Standard, if necessary.
Type Site Workers1.
8. Select OK .
Click
The Create New Base Calendar dialog box closes and the new base calendar appears in the Change Working Time dialog box.
Scroll to view the calendar for September 2018 and mark September 10-13 as an exception named Training.
9. Modify the new base calendar. The base calendar is modified.
10. Select OK .
Click
The Change Working Time dialog box closes and the changes to the base calendar are saved.
Practice the Concept: Create a new base calendar called Landscaping . Base the calendar on the Standard calendar.
Add Saturday as a working day in addition to Monday to Friday. Do this by going to the Work Weeks tab and then click the Details button. Select Saturday and Set days