Project 2016 - Introduction

Lesson – Working with Tasks

Project 2016

Entering a milestone task

NOTE You can also set a milestone using the Project Guide. From the Tasks pane, select the List the tasks in the project link, select the task you want to mark as a milestone, and then click the Make selected task a milestone check box in the List Tasks pane.

Procedures

1. Switch to the Gantt Chart view. 2. Select the field where you want to enter the milestone task. 3. Enter a name for the milestone task. 4. Select the Duration field. 5. Type a duration of 0 days for the milestone task. 6. Press [Enter] .

Step-by-Step

Enter a milestone task.

If necessary, open the House 2.mpp file. Click in the first empty field in the Task Name column.

Steps

Practice Data

1. Type a name for the milestone task. The milestone task name.

Type Complete Planning Phase .

2. Select the Duration field. The field is highlighted.

Press [Tab].

Page 46