Project 2016 - Introduction

Lesson – Working with Tasks

Project 2016

Steps

Practice Data

7. Select OK .

Click

.

The Recurring Task Information dialog box closes, the Gantt chart displays the recurring task, and a recurring task indicator appears to the left of the task in the Indicator column.

Point to the recurring task indicator to the left of the task name to view the information in the ScreenTip.

V IEWING AND H IDING R ECURRING T ASKS

Discussion

A recurring task appears on the task list as a single task in bold type with the recurring task indicator to its left. Although it appears as a single task, a recurring task is actually made up of several subtasks. Each subtask represents one occurrence of the task and can be viewed or hidden as desired. The number of subtasks depends on the duration of the task, since subtasks can be scheduled for the entire length of a project. Each subtask has a constraint indicator to its left, illustrating that the task should start no earlier than the date for which it is scheduled.

Viewing recurring tasks

Procedures

1. Switch to the Gantt Chart view. 2. Click the plus sign ( + ) to the left of the recurring task to view the subtasks. 3. Click the minus sign ( - ) to the left of the recurring task to hide the subtasks.