Project 2016 - Introduction
Lesson – Working with Tasks
Project 2016
Edit Subtasks
NOTE You can also open the Task Information dialog box by clicking Task Information or Recurring Task Information .
Procedures
1. Switch to the Gantt Chart view. 2. Double-click the subtask you want to edit. 3. Select the General tab.
4. Enter the desired duration for the subtask in the Duration spin box. 5. Select the Start or Finish list to select a new date for the subtask. 6. Select the new date for the subtask. 7. Continue to edit the recurring task as desired.
8. Select
.
Step-by-Step
Edit recurring tasks.
Page 52