Project 2016 Intermediate
Lesson – Tracking Your Progress
Project 2016
Procedures
1. Switch to the Gantt Chart view. 2. Select the task you want to mark as complete.
3. On the Task ribbon, Schedule group click the 100% Complete button .
Step-by-Step
From the Student Data directory, open HOUSE15.MPP . Update a completed task.
If necessary, switch to the Gantt Chart view.
Display the Task ribbon.
Steps
Practice Data
1. Select the task you want to mark as complete. The desired task is selected. 2. On the Task ribbon in the Schedule group click the 100% Complete button . The task is marked complete and the Act. Start and Act. Finish fields are completed.
Click the 2 Conduct Survey task, if necessary.
Click .
Notice that a checkmark appears in the Indicators field for the task and the progress bar extends the full length of the task bar.
Practice the Concept: Mark the 3 Develop Blueprints task as 50% complete. Notice that the progress bar only extends half the length of the task bar.
Display the Tracking table, if not already displayed, and drag the split bar as far right as possible. Notice the data that appears in the actual fields for the tasks updated with completed work. The 2 Conduct Site Survey task is marked as 100% in the % Comp. column. Since the task is complete, 0 days appears in the Rem. Dur.
Page 90
OFFICEPRO, Inc.