Lesson – Tracking Your Progress
Project 2016
Procedures
1. Switch to the Gantt Chart view. 2. Select the Task ribbon.
3. Click the Update as Mark on Track button
in the Schedule
group.
Step-by-Step
Update a task on schedule.
If necessary, switch to the Gantt Chart view. Apply the Tracking table, drag the split bar as far right as possible.
Note: The status date for this project is set to 6/16/18 .
Steps
Practice Data
1. Select the task in progress you want to update. The task is selected. 2. On the Task ribbon in the Schedule group, click the Mark on Track button. The appropriate fields for the task are updated or a Planning Wizard dialog box opens if the task has a constraint or deadline date.
Click 3 Develop Blueprints .
Click
.
Notice that the % Comp. column displays 80% since this task is scheduled to be completed on 6/20/18 .
Practice the Concept: Mark the task as 100% complete.