Lesson – Tracking Your Progress

Project 2016

Procedures

1. Switch to the Gantt Chart view. 2. Apply the Tracking table. 3. Select the Act. Start field for the desired task. 4. Enter the actual start date for the task. 5. Select the Act. Finish field for the desired task. 6. Enter the actual finish date for the task. 7. Press [Enter] .

Step-by-Step

Update a task not on schedule.

If necessary, switch to the Gantt Chart view and drag the split bar as far right as possible.

Apply the Entry table. Notice that the 4 Draft Proposal task is recorded as starting on 6/21/18 and finishing on 6/23/18. This task, however, started early and finished late. Apply the Tracking table.

Steps

Practice Data

1. For the 4 Draft Proposal task select the Act. Start field for the desired task. The Act. Start field is selected for the desired task. 2. Enter the actual start date for the task. The actual start date appears in the Act. Start field. 3. Select the Act. Finish field for the desired task.

Click the Act. Start field

Type 6/20/18.

Click the Act. Finish field.

The Act. Finish field is selected for the desired task.