Project 2016 Intermediate

Lesson – Tracking Your Progress

Project 2016

The Update Project dialog box

NOTE

A Planning Wizard dialog box opens if the time span includes a task with a constraint or deadline date. To update selected tasks only, select them before opening the Update Project dialog box and then select the Selected tasks option.

Procedures

1. Select the Project ribbon. 2. In the Status group select the Update Project command. 3. Enter the desired date in the Update work as complete through box. 4. Select additional options as desired.

5. Select

.

6. If a Planning Wizard dialog box opens, select

.

Step-by-Step

Update a project on schedule.

If necessary, switch to the Gantt Chart view and apply the Tracking table.