Project 2016 Intermediate

Lesson – Tracking Your Progress

Project 2016

The Progress Lines dialog box

NOTE

Display additional progress lines at various dates from the Progress Lines dialog box on the Dates and Intervals page using the Progress Line Dates list . To remove additional progress lines, open the Progress Lines dialog box and use the Delete button. Double-click an existing progress line to open the Progress Lines dialog box.

Procedures

1. Switch to the Gantt view. 2. Select the Gantt Chart Tools Format tab. 3. In the Format group from the Gridlines drop-down list, select the Progress Lines command. 4. Select the Dates and Intervals tab. 5. Select the Display option. 6. Select the At project status date or At current date option. 7. Continue to select options as desired.

8. Select

.

Page 114