Lesson - Customizing Project Information

Procedures

1. Select the File tab

.

2. Select the Options command.

3. Select Schedule . 4. Change the scheduling options as desired.

5. Select

.

Step-by-Step

Set scheduling options.

Switch to the Resource Sheet view and notice that the Max. Units field displays percentages.

Steps

Practice Data

1. Select the File tab.

Click

The Backstage screen appears.

Click Options.

2. Select the Options command. The Options dialog box opens.

Click Schedule .

3. Select Schedule .

The Schedule page appears.

Click Show assignment units as a: .

4. Select the Show assignment units as a: list. A list of options appears.

Click Decimal .

5. Select the desired option. The option is selected.

Select the Duration is entered in: list and select Hours .

6. Continue to change the scheduling options as needed. The options are changed.