Project 2016 Intermediate
Project 2016
Lesson – Adjusting Resources
4. In the Level group click
.
5. Select . 6. Select the Everyone option to level all resources or the Selected resources option to level only the resources that are currently selected.
Step-by-Step
Level a resource.
If necessary, switch to the Resource Usage view.
Scroll as necessary and notice that the 9 Carpenter resources appears in red with a leveling indicator to its left, indicating that it is overallocated. Note the end date of the project is Tues, 11/13/2018.
Steps
Practice Data
1. Select the resources you want to level if you are only leveling selected resources. The desired resource is selected.
Click the 9 Carpenter resource in the Resource Name column.
2. Click the Resource tab.
The Resource ribbon is displayed.
Click
.
3. In the Level group select the Level Resource command. The Level Resource dialog box appears.
Click
.
4. Select Level Now .
Click
.
The Level Resource dialog box closes and the resources are levelled.
Notice that the Carpenter resource no longer appears in red and that the leveling indicator disappeared. Note that the project end date did not change.