Project 2016 Intermediate
Project 2016
Lesson – Adjusting Resources
3. Select the Automatic option under Leveling Calculations .
4. Change other leveling options as needed.
5. Click
.
6. Select the Entire pool or Selected resources option, if applicable.
7. Click
, if applicable.
Step-by-Step
Change leveling to automatic.
Switch to the Resource Sheet view. Select the 1 Laborer resource, which appears in red, indicating that it is overallocated.
Steps
Practice Data
1. Select the Resource tab.
The Resource ribbon appears.
Click
.
2. Select the Leveling Options button. The Resource Leveling dialog box opens. 3. Select the desired option under Leveling Calculations . The desired option is selected. 4. Change any other leveling options as desired. The desired leveling options are changed.
Click
Click Automatic.
Click Level entire project under Leveling range for < file name>.
5. Select OK .
Click
The Resource Leveling dialog box closes, the automatic leveling feature is enabled, and the Level Now dialog box opens.
OFFICEPRO, Inc.
Page 21
Made with FlippingBook - professional solution for displaying marketing and sales documents online