Project 2016 Intermediate
Project 2016
Lesson - Assigning Costs
Procedures
1. Switch to the Resource Sheet view.
2. Select the View tab.
3. Select Details to split the pane.
4. Select the resource in the top pane for which you want to select an accrual method. 5. Click in the Accrue at field in the bottom pane to activate it.
6. Select the Accrue at list.
7. Select the desired accrual method for the resource.
8. Select
.
Step-by-Step
Select an accrual method.
If necessary, switch to the Resource Sheet view and split the window to display a combination view with the Resource Form.
Steps
Practice Data
1. Select the resource in the top pane for which you want to select an accrual method. The resource is selected and the bottom pane changes to display information about the resource. 2. Click in the Accrue at field in the bottom pane to activate it. The Accrue at field is activated.
Click the 2 Painter resource.
Click in the Accrue at field in the bottom pane.
3. Select the Accrue at list.
Click Accrue at .
A list of the three available accrual methods appears.