Lesson – Working with Baselines
your project plan, the bars no longer align if your changes affect the task start and end dates.
The Tracking Gantt view
NOTE
The Tracking Gantt view displays Gantt bars for critical tasks in red.
Procedures
1. Select the Task tab.
2. Select the Gantt Chart drop-down.
3. Select the Tracking Gantt .
Step-by-Step
Use the Tracking Gantt view.
Steps
Practice Data
1. Select the Task tab.
The Task ribbon is visible.