Project 2016 Intermediate
Project 2016
Lesson – Working with Baselines
Procedures
1. Save an original baseline, if necessary.
2. Make changes to the project plan.
3. Click the
tab.
4. In the Scheduling group click
.
5. Select
in the list box.
6. If necessary, select the For: Entire project option.
7. Click
.
8. Click
to overwrite the old baseline.
Step-by-Step
Update a project baseline.
If necessary, display the Tracking Gantt view.
Insert a new task above the 6 Request Permits task. Name the task Review Bids and give the task a duration of 3 days . Then, assign the Contracting Specialist to the task. Scroll to view the Tracking Gantt bar for the new task, 6 Review Bids . There is no gray baseline bar for the new task. Notice the spread between the baseline (gray) and scheduled (blue) tracking bars for tasks 7 through 9.
Steps
Practice Data
1. Click the Project tab.
The Project ribbon appears.
Click
.
2. Click the Set Baseline button.
The Set Baseline submenu appears.
Click
.