Lesson 4 – Working with Resources

Using the Task Details Form view

NOTE

The Task Detail Form and the Task Form show similar information and are interchangeable. For this chapter we will be using the Task Detail Form. When you display a task view in the top pane, you can use the Previous and Next buttons in the Task Details Form view to navigate through the task list. You can also add resources in the Task Information dialog box. You can open this dialog box by double-clicking the task, selecting the Resources tab and using the Resource Name and Units fields to add the desired resources. A smart tag does not appear if you add a resource using the Task Details Form view in a combination window.

Procedures

1. Switch to the desired view. 2. Select the Task ribbon. 3. Select the Details button in the Properties group. 4. Activate the bottom pane. 5. To change the details displayed by Right Click on the Form. 6. Select the form containing the details you want to display.

OFFICEPRO, Inc.

Page 101

Made with FlippingBook HTML5