Project 2013 Introduction
Lesson 4 – Working with Resources
Project 2013
E XERCISE
W ORKING WITH R ESOURCES
Task
Work with resources.
1. Open Rooms6 .
2. Create the following work and material resources in the resource sheet: ( Hint: Be sure to indicate the resource type. )
Resource Name
Resource Type
Material Label
Initials Group
Max. Units
Carpet Layer
Work
n/a
CL
Contractor
200%
Electrician
Work
n/a
E
Union
300%
Computer Technician
Work
n/a
CT
Contractor
200%
Computers
Material
units
CP
Supplies
Carpet
Material
square feet
CR
Supplies
Inspection Fees
Cost
n/a
IF
Fees
Permit Fees
Cost
n/a
PF
Fees
3. Assign the resources as follows:
ID
Task
Resource(s)
Units
10
Install Light Fixtures
Electrician
100%
12
Lay Carpets in Board Room Install Board Room Furniture Electrical Adjust - Computer Room
Carpet Layer Carpet
200% 600 square feet
13
Laborer
200%
16
Electrician
300%
Page 110