Project 2013 Introduction

Lesson 1 – Learning Project Basics

Project 2013

NOTE If you change the settings on the Calendar page in the Options dialog box and then select the Set as Default button, each new project will be scheduled according to these settings. For this reason, you should not select this button unless all of your projects will be scheduled according to these settings. For example, if you set a project to have a seven hour work day, each new project will default to a seven hour work day.

Procedures

1. Select the Project tab on the Ribbon.

2. Click the

icon in the Properties group.

3. Click the

tab.

4. Click the button. 5. Make any necessary changes in the Details dialog box.

6. Select the desired options and select

.

7. Select

.

Step-by-Step

We will change the working times to 9:00 AM to 6:00 PM, with one hour for lunch.

From the Student Data directory, open HOUSE1.MPP.