Project 2013 Introduction

Project 2013

Lesson 1 – Learning Project Basics

Define the project working times.

Steps

Practice Data

1. Click the Change Working Time icon in the Project tab. Opens the Change Working Times window

Click

.

2. Select the Work Weeks tab.

Click

.

A list of base calendars appears.

3. Select the Detail button.

Click

.

Opens the Work week detail dialog box.

4. Select the Day(s) wish to change. The desired days are selected.

Select Monday, hold down [Shift] click on Friday. Set day(s) to these specific working times. Click

5. To change the working hours, select the Set day(s) to these specific working times: The option is selected. 6. Click in a cell to enter a new start time. The cell is selected.

Click in first cell in the From field.

7. Enter the desired times.

Type 9:00 AM and press Right Arrow Key. Type 1:00 PM in the corresponding To box and click in the From box on the second line. Type 2:00 PM and press the Right Arrow Key .

The desired start time is entered.

8. Set the desired end time.

The desired end time is entered.

9. Set the desired time in the From field. The desired start time for the afternoon is entered.

10. Enter the desired End time. The desired end time is set.

Type 6:00 PM and press the [Enter] key.

11. Select OK .

Click

.

The Work Week dialog box closes and the options are saved.